      • Infrastructure pipeline crosses Rs 38 lakh crore; 649 projects achieve over 80% physical progress
      Economy

      Infrastructure pipeline crosses Rs 38 lakh crore; 649 projects achieve over 80% physical progress

      Email :2

      The Centre is overseeing an infrastructure pipeline worth Rs 38.11 lakh crore, with Rs 17.87 lakh crore already spent on 1,862 ongoing projects as of October 2026, according to the latest monthly Flash Report of the Ministry of Statistics and Programme Implementation (MoSPI).

      The expenditure represents 46.88 per cent of the latest combined project cost, while 649 projects have crossed 80 per cent physical progress and another 326 have exceeded 80 per cent financial completion.

      Transport and logistics account for the largest share of the pipeline, with 1,324 projects worth Rs 20.37 lakh crore, followed by energy with 229 projects valued at Rs 11.31 lakh crore. Together, the two sectors account for 1,553 projects, or 83.4 per cent of the projects under monitoring.

      Project Progress

      The monitoring data indicates that a substantial share of the projects has moved into advanced stages of execution. As of October, 649 projects, or about 35 per cent of the total, had crossed 80 per cent physical progress, while 326 projects, or around 18 per cent, had exceeded 80 per cent financial completion. The portfolio comprises 790 mega projects with individual costs of Rs 1,000 crore or more and 1,072 projects below the Rs 1,000 crore threshold.

      Transport Leads Pipeline

      Transport and logistics form the largest component of the infrastructure pipeline, with 1,324 projects valued at Rs 20.37 lakh crore. The category represents 71.1 per cent of the monitored projects and about 53.45 per cent of their aggregate cost. It covers roads and highways, railways, urban public transport, aviation, shipping and logistics infrastructure.

      Roads and highways account for 972 projects, while railways account for 290. Together, the two sub-sectors represent about 95.3 per cent of the category’s project cost. Cumulative expenditure in transport and logistics has reached Rs 10.31 lakh crore, equivalent to 50.64 per cent of the category’s project cost.

      Shipping records the highest expenditure-to-cost ratio among the transport and logistics sub-sectors at 66.14 per cent, followed by logistics infrastructure at 56.36 per cent. Railways, aviation and aviation infrastructure, urban public transport, and roads and highways record expenditure ratios of 50.51 per cent, 54.06 per cent, 49.07 per cent and 51.02 per cent, respectively.

      Energy Pipeline

      Energy comprises 229 projects with a combined cost of Rs 11.31 lakh crore, accounting for about 29.68 per cent of the total revised project cost. Oil and gas has the highest number of projects at 104, while electricity generation represents the largest project cost at Rs 4.27 lakh crore across 38 projects.

      Cumulative expenditure in the energy category stands at Rs 4.47 lakh crore, or 39.49 per cent of the project cost. Energy storage records the highest expenditure ratio at 83.75 per cent, followed by oil and gas at 50.17 per cent. Electricity generation and transmission and distribution have expenditure ratios of 33.51 per cent and 27.56 per cent, respectively.

      Ministry-Wise Progress

      The Ministry of Road Transport and Highways accounts for the largest number of projects, with 972 projects representing 52 per cent of the total. These projects have a combined revised cost of Rs 9.55 lakh crore. The Ministry of Railways follows with 288 ongoing projects valued at Rs 7.38 lakh crore.

      The Ministry of Coal has 121 projects worth Rs 2.22 lakh crore, while the Ministry of Petroleum and Natural Gas has 117 projects with a combined cost of Rs 4.42 lakh crore. The Ministry of Power accounts for 108 projects worth Rs 6.55 lakh crore, while the Ministry of Housing and Urban Affairs has 50 projects valued at Rs 3.44 lakh crore.

      The Department of Water Resources, River Development and Ganga Rejuvenation has 33 projects worth Rs 1.93 lakh crore. The remaining 173 projects, with a combined cost of Rs 2.63 lakh crore, are spread across departments and ministries including higher education, civil aviation, steel, telecommunications, labour and employment, ports, shipping and waterways, health and family welfare, mines, industry promotion and sports.

      Completed Projects

      Several major projects reached commissioning during October. A Rs 4,445 crore transmission project for integrating renewable energy zones in Karnataka was commissioned on 16 October. The project covers Phase II of Koppal II and Phase I of Gadag II.

      A six-lane elevated corridor on NH-66, involving an investment of Rs 641.46 crore, was also commissioned. Separately, the Ministry of Steel completed the Rs 884.1 crore rebuilding of Coke Oven Batteries 7 and 8 at Bhilai Steel Plant on 30 October.

      New Projects Added

      The government added 38 projects to the PAIMANA monitoring system during October. The Ministry of Road Transport and Highways accounted for 23 of these, followed by the Ministry of Steel with five and the Ministry of Power with three. The Ministry of Petroleum and Natural Gas and the Ministry of Housing and Urban Affairs added two projects each, while the Department of Higher Education added two and the Ministry of Railways one.

      Among the newly monitored projects is an eight-lane access-controlled highway connecting Vadhavan Port to the junction at NH-48, with a cost of Rs 4,464 crore.

      Another project involves four-laning of the Badnawar-Petlawad-Thandla-Timarwani section of NH-752D in Madhya Pradesh, from Badnawar Bypass to the Timarwani Interchange of the Delhi-Mumbai Expressway, at a cost of Rs 3,842.41 crore.

      The new additions also include Ahmedabad Metro Rail Project Phase 2A, covering Koteshwar Road to Airport, at Rs 2,169.04 crore, and Phase 2B, covering GIFT City to Shahpur, at Rs 1,067.35 crore.

      Other Infrastructure

      The communication category comprises 31 telecommunications projects with a combined cost of Rs 1.34 lakh crore and cumulative expenditure of Rs 65,227 crore, equivalent to 48.78 per cent of the project cost.

      Social and commercial infrastructure comprises 79 projects worth Rs 95,305 crore, with cumulative expenditure of Rs 38,563 crore, or 40.46 per cent of the project cost. The category covers education, healthcare, real estate, and tourism, hospitality and wellness.

      The ‘Others’ category includes 151 projects worth Rs 2.18 lakh crore across coal, steel, metals and mining and construction. Cumulative expenditure stands at Rs 67,429 crore, representing 30.95 per cent of the combined project cost. Coal accounts for 115 projects worth Rs 1.83 lakh crore.

      0 0 votes
      Article Rating
      Subscribe
      Notify of
      guest
      0 Comments
      Oldest
      Newest Most Voted

      Related Posts

      Join

      To Receive Daily Updates

      0
      Would love your thoughts, please comment.x
      ()
      x