  • Delhi–Mumbai Expressway Nears Completion: Key sections achieve major milestones across states
News

Delhi–Mumbai Expressway Nears Completion: Key sections achieve major milestones across states

Delhi–Mumbai Expressway
Email :14

The Delhi–Mumbai Expressway — India’s longest and most ambitious greenfield infrastructure project — continues to record steady progress, with several key stretches approaching completion. The 1,386-km corridor, designed to cut travel time between the two metros to under 12 hours, has achieved major construction milestones across multiple states.

The Delhi–Vadodara section now has 27 of its 31 packages operational, while the Vadodara–Virar stretch and crucial connectivity spurs to the NCR and JNPT are also advancing rapidly, underscoring the project’s momentum and the participation of leading infrastructure players such as Larsen & Toubro, GR Infraprojects, HG Infra, and Ashoka Buildcon, according to a report by The Free Press Journal.

The Delhi–Mumbai Expressway, one of India’s most ambitious infrastructure projects, continues to make steady progress across multiple sections. The Delhi–Vadodara stretch, covering 31 packages, has achieved significant milestones. Out of these, 27 packages are already operational across Haryana, Rajasthan and Madhya Pradesh. Packages 10 and 15 in Rajasthan, and Package 26 in Gujarat, are nearing completion with 94 per cent, 82 per cent and 74 per cent progress respectively.

The 1,386-km-long corridor’s Delhi–Vadodara section involves leading infrastructure firms such as APCO Infratech, HG Infra, GR Infraprojects, Larsen & Toubro, and GHV India. Notably, Larsen & Toubro’s Package 11 and GR Infra’s multiple packages across Rajasthan and Madhya Pradesh have achieved 100 per cent completion.

The Vadodara–Virar section, consisting of 13 packages, also shows strong advancement. Among them, six packages are fully operational, while others are in the final stages. Package 5, spanning 25 km from Ankleshwar to Kim, executed by Sadbhav Engineering and Gawar Construction, has shown marked improvement, with completion status rising to 86 per cent from 82 per cent last month.

GR Infra, Ashoka Buildcon, and Patel Infrastructure are among the firms driving this phase forward. Packages 8 and 9, awarded to Roadways Solutions India Infra, currently stand at 5 per cent and 40 per cent completion respectively, while Package 12 by Montecarlo in Maharashtra has reached 85 per cent progress.

The DND–Faridabad–KMP Spur, which connects the National Capital Region to the main expressway, is close to completion. Out of the four packages, three are fully operational in Haryana, while the Jewar Spur package by APCO Infratech has recorded 56 per cent completion, up from 54 per cent previously.

The Jawaharlal Nehru Port Trust (JNPT) Spur in Maharashtra is also nearing completion. Package 15 by Agroh Infrastructure has achieved 86 per cent progress, while Package 18 has merged with MSRDC’s Virar–Alibaug Multi-Modal Corridor Project. Other packages under IRCON and Shivalaya Construction are between 77 per cent and 82 per cent complete.

0 0 votes
Article Rating
Subscribe
Notify of
guest
0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments

Related Posts

Join

To Receive Daily Updates

0
Would love your thoughts, please comment.x
()
x